In the first construction phase, one-way traffic will be possible on one side of Bahnhofstraße coming from the roundabout. From the direction of Münsterstraße/Konrad-Adenauer-Platz, Bahnhofstraße will be closed on one side and will not be passable for the duration of the first construction phase of approx. three weeks. The corresponding diversion leads via Münsterstraße, Hansaring and finally ends at the Fürstenhof/Bahnhofsstraße roundabout. The footpath and cycle path on the Werne adult education centre side will also be closed. Here it will be possible to use the footpath and cycle path opposite. For the second construction phase, the other side of the carriageway will be closed on one side. Thyssengas will provide separate information on this.
The planning and implementation of the measure was carried out in close consultation with representatives of the town of Werne. Thyssengas asks for your understanding for the resulting inconvenience.