Checking the connection enquiry
Once we have received your enquiry, we will confirm that the documents you have submitted are complete or inform you of any details that are still missing. We will then check as quickly as possible whether we can realise the project under your specified conditions. Depending on your requirements, we will arrange coordination meetings with you, answer any open questions or coordinate with you directly on site at the planned connection point.
The technical minimum requirements (TMA) for grid coupling and grid connection apply to the realisation of the connection. Please use our checklist in the download area as a guide when checking the TMA. There are no costs for the check.
Realisation contract
If we can provide the capacity, we will get in touch with you regarding the technical details and the design of the connection point and transfer these into a realisation contract. As soon as this has been signed, we will start realising the project.
This is followed by the signing of other contracts required for subsequent commissioning, such as the grid connection or grid coupling contract. We conclude the grid access contract for the actual utilisation of the connection with either you or your supplier.
Commissioning
As soon as our connection line is connected to your gas pressure regulator and metering system (GDRM), all contracts have been signed and we confirm commissioning, the connection can go into operation. From now on, we will be happy to answer any questions you may have during operation.
Checklist of verifiable minimum technical requirements Documents