Transmission system operator Thyssengas is carrying out pipeline construction work in the Marienbrücke area in Arnsberg – half of Uferstraße will be closed from 20 January 2026.

From Tuesday, 20 January 2026, the transmission system operator Thyssengas will continue the pipeline construction work, some of which is related to the renovation of the Marienbrücke bridge by the city of Arnsberg. As a result, half of the road will be closed on Uferstraße (house numbers 1 to 3) over a length of approximately 80 metres. Traffic will be able to continue flowing along the construction site for the duration of the work. The work will take approximately six weeks in total and, according to current plans, will be completed at the beginning of March 2026.

The planning and implementation of the measure are being carried out in close consultation with representatives of the city of Arnsberg. The measure described is related to the Ruhrtalleitung construction project.

To the press release

Back