Update: Transmission system operator Thyssengas is carrying out pipeline construction work on Odacker Weg and Risnei Weg in Warstein

Since Monday, 17 June 2024, the transmission system operator Thyssengas has been carrying out pipeline construction work on Odackerweg and Risnei Weg in Warstein. Since the start of the construction work, the end of Odackerweg and Risnei Weg up to the junction with Forstweg have been impassable. Due to delays in the construction process, the measure will be extended by a further four weeks. The closure of this section of the road will therefore remain in place. According to the current planning status, the work will be completed by mid-September.

The planning and implementation of the measures will be carried out in close consultation with representatives of the town of Warstein and the Soest-Sauerland regional forestry office. Thyssengas asks for your understanding for the resulting inconvenience.