The first section of the project will begin on 5 February 2025 on Kämpchenstraße and will extend over a length of around 140 metres from number 41 to house number 13. The work will result in a one-sided closure in this section and is expected to last until March 2025. Traffic can continue to flow along the construction site and will be regulated by a mobile traffic light system. The entrance and exit to Nobelstraße will be closed at the junction with Kämpchenstraße. A corresponding diversion will be signposted. This will lead via the street "In der Leer" and Klosterstraße. Pedestrians are requested to use the other side of the road.
The planning and realisation of the measure will be carried out in close coordination with representatives of the town of Herzogenrath. Thyssengas asks for your understanding for the resulting inconvenience. Information on the second construction phase is the subject of a separate communication.