The first section of the project will begin on 29 January 2025 in the field on the farm track between Stetternicher Straße and Steinstraßer Allee. As a result, there may be slight traffic restrictions in this area. Overall, the work in this construction phase will take around three months and, according to current planning, will be completed in mid-May 2025.
The planning and implementation of the measure will be carried out in close coordination with representatives of the district of Düren and the city of Jülich. Thyssengas asks for your understanding for the resulting inconvenience. Information on the second construction phase is the subject of a separate communication.