#H2EltenStHubert

Hydrogen pipeline Elten-St.Hubert

Hydrogen from the Netherlands to the Ruhr region

For the hydrogen ramp-up in Germany, we are providing the connection to the emerging European hydrogen infrastructure. By converting an existing natural gas pipeline, we will realise a section of a central corridor for hydrogen transport from the Netherlands between Elten (Emmerich am Rhein) and St. Hubert (Kempen) by the end of 2030.

The conversion of the approximately 68-kilometre-long pipeline will enable large quantities of H2 to be transported to the Ruhr region and provide industry, SMEs and distribution network operators in the region with an H2 supply perspective.

In 2025, the technical survey of the pipeline and coordination with the authorities are on our agenda. In 2026 to 2027, the pipeline conversion will then begin with local construction measures. Local information events are planned in advance.

Icon einer Route zwischen zwei Standorten als Symbol für die Thyssengas Biogas-Netzkarte.

The following municipalities are in the direct catchment area of the H2 pipeline project:

  • District of Kleve, town of Emmerich am Rhein, town of Kleve, municipality of Uedem, municipality of Bedburg-Hau, town of Kalkar, municipality of Kerken
  • District of Wesel, town of Xanten, town of Sonsbeck, town of Rheinberg, town of Moers, town of Kamp-Lintfort, town of Neukirchen-Vluyn
  • District of Viersen, City of Kempen
  • District-free city of Krefeld
Icon mit Werkzeug als Symbol für den Projekttyp "Umstellung der Leitung" auf Wasserstoff.

Project type:

Line conversion

Icon eines Strategieplans als Symbol für die Projektphase "Planung & vorbereitende Maßnahmen".

Project phase:

Planning & preparatory measures

Icon mit Zielflaggen als Symbol für die geplante Inbetriebnahme des H2-Projekts.

Planned Commissioning:

End of 2030

Icon einer Wegstrecke als Symbol für die Leitungslänge.

cable length:

around 68 kilometres

Icon eines Winkelmaßes als Symbol für den Leitungsdurchmesser.

Cable diameter:

DN 900 (90 cm)

Icon eines Schildes zwischen zwei Linien als Symbol für den Schutzstreifen.

Protective strip:

5 m on both sides of the line

Our project plan (planning status Q2/2025)

2024-2025

  • Stocktaking of the management
  • Planning the changeover measures
  • Stakeholder discussions

2026-2027

  • Preparation & start of the changeover measures
  • Stakeholder discussions

2027-2029

  • Implementation of the conversion measures
  • Stakeholder discussions, local information events & construction communication

2030

  • Completion of the conversion measures
  • Technical acceptance & commissioning
  • Start of recultivation work

The project Q&A

With our H2 pipeline network, we are connecting the region to the future hydrogen motorways in Germany. Municipalities, industry and SMEs thus gain an H2 supply perspective and the opportunity to organise energy-intensive processes sustainably with the help of hydrogen.

Interested municipalities and companies can use our contact form to report their requirements for hydrogen feed-in or feed-out at any time. We will then check the possibility of a connection to our H2 infrastructure.

Municipalities also play a central role in our project beyond the H2 supply. After all, they are important partners for the successful realisation of the project. This is why we seek dialogue shortly after the start of the project in order to develop the best solution together with local stakeholders and those affected.

For a conversion, the strict regulations of the Energy Industry Act and the Ordinance on High-Pressure Gas Pipelines must be complied with. The same high safety standards apply to H2 pipelines as to natural gas pipelines. Each pipeline is checked in advance by an independent expert to ensure that it is suitable for hydrogen. Specific measures that must be carried out before the changeover are recorded (e.g. technical adjustments, measurement of the pressure curve, adjustment of maintenance intervals for leak checks). Before the pipeline is commissioned, it is then approved by an independent expert. Our colleagues from the network control centres then take over and ensure safe operation through regular inspections and maintenance.

Hydrogen is gaseous and can be stored in the same way as natural gas and transported to consumers in gas pipelines. Thyssengas already has an extensive network with around 4,400 kilometres of pipeline. Converting existing pipelines for H2 transport is sustainable and involves less interference with nature and the environment. Of course, conversion is also faster, as pipeline routes no longer need to be developed and authorised.

For us, proactive information and dialogue are an integral part of all pipeline construction projects. From the early planning phase onwards, we inform all those affected about the current status of the project at regular intervals - for example via press releases and on our website. Our on-site dialogue and information events also offer the opportunity to enter into a direct exchange with us and ask questions about the project.

No, the transport of hydrogen via pipelines is a proven and safe technology. The same high safety standards apply to H2 pipelines as to natural gas pipelines. Thyssengas has over 100 years of experience in gas transport and is continuously developing proven control and maintenance processes. Safety is always our top priority - this applies to the construction, operation and maintenance of our pipelines.

Whether natural gas or hydrogen. Our pipelines are monitored 365 days a year. The experts in the network control centres are on duty around the clock, checking the pipelines, organising maintenance and coordinating construction measures in the catchment area of our pipeline network. Regular inspections and aerial surveys of the routes ensure additional safety.

For the construction of the pipeline, a construction strip up to 40 metres wide will be created along the route. The measures required for this, such as earthworks and tree felling, are part of the approval process in advance. Once the work has been completed, the construction strip will be recultivated. A protective strip between two and six metres wide will remain to the right and left of the pipeline, but this can be used for agricultural purposes without any restrictions.

During the construction work, the areas affected by the construction work cannot be used for agricultural purposes. Any damage incurred (e.g. crop failure) will of course be reimbursed. After recultivation, normal agricultural use can be resumed immediately. The permissible cultivation depth of the field / field in the protective strip to the right and left of the pipeline is generally up to 60 centimetres.

Blau getöntes Bild: Thyssengas-Mitarbeiter blickt auf Windräder, Symbol für den Transport von Wasserstoff (H2).

Together into the energy future

In our projects, we work together with local stakeholders to find the best solution! We focus on dialogue, transparent information, personal discussions and local events. You can contact the project team at any time by e-mail:

projekte@thyssengas.com

Rommerskirchen-Wesseling hydrogen pipeline system
In the Rhineland, for the H2 supply of tomorrow.
Coesfeld-Rinkerode hydrogen pipeline
Hydrogen for the Münsterland and Westphalia.